An application may be submitted once the interconnecting utility grants final approval to operate as indicated by an official approval notice, the system is placed online, and production is recorded. Eligible generation begins the date a fully completed application is submitted to the PA AEPS Program Administrator or the date of interconnection approval, whichever is later. Any generation prior to the later of the two dates is not eligible to earn credits.